Sylvenstein Reservoir Improvement

In order to improve flood protection on the Isar River, the height of the dam was increased by three metres and a second spillway was created from 1994 to 2001.  A second hydroelectric power plant providing 3.8 megawatt was also installed.

The dam is currently being improved with a diaphragm (70 m depth) wall, an inspection tunnel and a seepage water system. The inspection tunnel is being built by pipe jacking. For this purpose an access tunnel as well as a launch and receiving cavern with corresponding shaft have to be built by drill and blast method.

Client
CDM Smith Consult GmbH / Water Management Authority Weilheim

Construction Period of current Dam Improvement
2011 to 2015

Brief
Project planning
Structural design
Site supervision