Reichenbach Bridge Utility Tunnel

The Isar tunnel was created during reconstruction of the "Links der Isar" main sewer line. The tunnel was executed as a rectangular cross-section utility tunnel using the bored pile cut-and-cover method with associated superstructures and side channel. The cross-section contains a City of Munich utility water supply line with a diameter of 800 mm.

Client
City of Munich, Sewage Treatment Works


Construction Period
2007 to 2010


Brief

Project planning, site supervision, site management, health and safety coordination during planning and construction phases